DONGSHENG Factory

Industrial Utilities · Cooling Water and Material Feeding

CNHAO delivered an industrial cooling water system and a central feeding system for DONGSHENG Factory as one package: both systems handed over on the same schedule, with plant utilities and production lines commissioned together and full output reached on the first start-up.

CLIENT

DONGSHENG Factory

SOLUTION

Industrial Cooling Water · Central Feeding

APPLICATION

Plant Utilities and Production Lines

DELIVERY

Dual Systems, One Commissioning

Cooling Water and Central Feeding Systems for DONGSHENG Factory

Two systems, one schedule — cooling water and central feeding were delivered together, so the plant’s utilities and its production lines went into operation on the same day.

DONGSHENG needed its industrial cooling water system and its central feeding system running before the lines went live. CNHAO supplied both as a single package, engineered and installed on one timetable instead of as two separate projects handed over at different times.

Because utilities and lines were commissioned together, pipework, pumping capacity, cooling capacity and material conveying were all checked against the same start-up date — no waiting for a second contractor, and no gap between a plant that is ready and a line that can run.

Cooling water and material feeding are the two utilities that decide whether a new line actually produces: one holds process temperature, the other keeps every machine fed. Delivering both inside the same window is why the plant reached its planned output during the first commissioning rather than ramping up in stages.

Why it matters

Split utilities between two suppliers and the schedule usually slips twice — once for cooling, once for feeding. One package, one schedule, one commissioning: the lines started on the date they were planned to start, and held their rate from there.

FAQs

What did this project include?

An industrial cooling water system and a central feeding system — engineered, installed and commissioned together as one package.

Were the two systems delivered at the same time?

Yes. Both were built and handed over on one schedule, so the plant utilities and the production lines went into operation together.

Did the line reach full output immediately?

Yes. Both systems were signed off in a single commissioning window, and the line reached its planned output during that commissioning rather than after a staged ramp-up.

Can the systems be extended later?

Yes. Cooling capacity and the conveying network were specified with headroom, so additional machines or cooling loops can be added without replacing the core equipment.

INDUSTRIAL COOLING WATER

Process cooling water supplied at stable temperature and pressure across the plant.

CENTRAL FEEDING

One conveying network delivering material to every machine on the line.

SYNCHRONISED DELIVERY

Utilities and production lines installed and started up on one timetable.

FIRST-TIME START-UP

Planned output reached during the first commissioning, with no staged ramp-up.